Courseiva
PRINCE2 PracticeshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

Which of the following best describes the difference between a risk owner and a risk actionee?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Risk owner manages the risk; risk actionee implements planned responses

The risk owner is responsible for managing the risk; the risk actionee is responsible for carrying out specific actions.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • There is no difference; they are the same

    Why it's wrong here

    They are distinct roles.

  • Risk owner manages the risk; risk actionee implements planned responses

    Why this is correct

    Correct: owner manages, actionee does the work.

  • Risk owner identifies the risk; risk actionee logs it

    Why it's wrong here

    Both may be involved in identification; roles are about management vs action.

  • Risk owner is always the Project Manager; risk actionee is a team member

    Why it's wrong here

    Risk owner can be any appropriate person, not necessarily PM.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.