Which of the following best describes the purpose of the Highlight Report?

⚠ Common exam trap

PRINCE2F often tests the confusion between Checkpoint, Highlight, and Exception Reports — candidates must remember the sender/receiver pair (Team→PM, PM→Board, PM→Board-on-breach) rather than just the report name.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

It is a report from the Project Manager to the Project Board on stage progress

In PRINCE2, the Highlight Report is produced by the Project Manager and sent to the Project Board at a frequency defined in the Communication Management Strategy, summarizing stage progress, status, and any forecast issues. It is the primary mechanism for the Board to exercise 'manage by exception' between stage boundaries.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    It is a report from the Team Manager to the Project Manager on work package progress

    Why it's wrong here

    A report from the Team Manager to the Project Manager on work package progress is the Checkpoint Report, not the Highlight Report. It is tempting because both are progress reports, but the Highlight Report is produced by the Project Manager for the Project Board at a defined frequency.

  • ✓

    It is a report from the Project Manager to the Project Board on stage progress

    Why this is correct

    The Highlight Report is produced by the Project Manager for the Project Board, summarising stage progress, status and any exceptions. This satisfies the stem by identifying both the sender and recipient, distinguishing it from Checkpoint Reports, which stay within the team.

  • ✗

    It is a report used to escalate tolerance deviations

    Why it's wrong here

    Escalating tolerance deviations is the purpose of an Exception Report, raised when a stage or project is forecast to exceed its tolerances. The Highlight Report tempts because it also flows to the Project Board, yet it provides routine progress information rather than triggering exception escalation.

  • ✗

    It is a report from the Project Board to stakeholders on overall project status

    Why it's wrong here

    The Highlight Report is produced by the Project Manager for the Project Board, not issued by the Board to stakeholders; that upward flow describes the End Stage Report or Project Board communications. It tempts because boards do communicate status, but the Highlight Report's defined origin is the Project Manager.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.