PRINCE2F PRINCE2 Practices Practice Question
A project's Stage Plan shows the work for the next stage. Which plan details the work for a team to produce one or more products?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Team Plan
A Team Plan is created by the Team Manager to detail the work needed to deliver the products assigned in a Work Package. Stage Plans cover an entire stage; the Project Plan covers the whole project; Exception Plans replace a plan when tolerances are exceeded.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Stage Plan
Why it's wrong here
A Stage Plan covers the entire stage, not just a team's work.
- ✗
Exception Plan
Why it's wrong here
An Exception Plan replaces a Stage or Project Plan when tolerances are exceeded.
- ✗
Project Plan
Why it's wrong here
The Project Plan covers the entire project timeline and major products.
- ✓
Team Plan
Why this is correct
A Team Plan details the work for a team to deliver products assigned in a Work Package.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.