Process — Managing Technical AspectshardMultiple ChoiceObjective-mapped

What to Do When Planned Risk Mitigation Fails on the Critical Path

During a complex construction project, a key vendor notifies you that they cannot deliver a critical component for another 4 weeks. This component is on the critical path and has no float. You have identified this risk in the risk register with a planned response of 'mitigate' by having a backup vendor. However, the backup vendor also cannot deliver on time. What should you do first?

Quick Answer

The correct first step is to evaluate alternative options such as fast-tracking other activities or sourcing from a different vendor, and then communicate the impact to stakeholders. This is because when a planned risk mitigation fails on the critical path, the project manager must immediately move to implement a contingency or fallback plan, not simply accept the delay. The technical concept here is that the risk response failure triggers a secondary response from the risk register, and since the critical path has zero float, any delay directly extends the project duration unless alternative schedule compression techniques are applied. On the PMP exam, this scenario tests your ability to prioritize proactive problem-solving over reactive blame or documentation; a common trap is choosing to “update the risk register” first, but the correct sequence is to evaluate options before formally logging the failure. Remember the mnemonic “Eval then Comms” — evaluate alternatives first, then communicate the impact to stakeholders.

⚠ Common exam trap

The trap here is that candidates often jump to escalation (A) or acceptance (B) without first exhausting the project manager's authority to evaluate and implement alternative responses, confusing a failed risk response with an immediate need for a change request.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Evaluate alternative options such as fast-tracking other activities or sourcing from a different vendor, and then communicate the impact to stakeholders

As the project manager, your first duty is to analyze the situation and identify feasible alternatives (e.g., sourcing from a different vendor, fast-tracking other critical path activities) before escalating or accepting the delay. The risk response (mitigate via backup vendor) has failed, so you must reassess options and then communicate the impact to stakeholders, as per the iterative risk management process in the PMBOK Guide.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Escalate the issue to the project sponsor and request a schedule extension

    Why it's wrong here

    Escalation may be necessary, but the PM should first explore options to recover the schedule before requesting an extension.

  • Accept the delay and update the project schedule accordingly

    Why it's wrong here

    Acceptance is a valid risk response, but the PM should first attempt to find a way to minimize the delay before simply accepting it.

  • Evaluate alternative options such as fast-tracking other activities or sourcing from a different vendor, and then communicate the impact to stakeholders

    Why this is correct

    The PM should proactively explore options to mitigate the delay and then communicate with stakeholders about the situation and potential solutions.

  • Immediately crash the schedule by adding resources to other activities to compress time

    Why it's wrong here

    While schedule compression may be needed, the first step should be to evaluate alternatives and communicate with stakeholders.

About these practice questions

This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During a construction project, a key vendor informs you that a critical component will be delayed by three weeks due to a raw material shortage. The component is on the project's critical path. What should you do FIRST?

medium
  • A.Check the risk register for the pre-planned risk response and implement it
  • B.Immediately inform the sponsor and ask for more budget to expedite the component
  • C.Negotiate with the vendor to shorten the delay without additional cost
  • D.Update the project schedule and inform stakeholders of the delay

Why A: The correct first action is to check the risk register for a pre-planned risk response. Since the component is on the critical path, any delay directly impacts the project completion date. A well-managed project would have identified this risk (raw material shortage) during planning and documented a response strategy (e.g., alternative sourcing, buffer stock). Implementing that pre-planned response is the most efficient and proactive step, aligning with the PMBOK Guide's guidance on executing risk responses.