Courseiva
Process — Managing Technical AspectseasyMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

Your project is using a predictive approach, and you have just completed the work breakdown structure (WBS). What is the NEXT step in project planning?

⚠ Common exam trap

It's easy for candidates to confuse the order of planning processes, thinking cost estimation or risk identification comes immediately after the WBS, when in fact the schedule must be developed first to provide the basis for those estimates.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Sequence the activities and develop the project schedule

After completing the WBS, the next step in a predictive (waterfall) project is to sequence the activities and develop the project schedule. The WBS decomposes deliverables into work packages, but the schedule requires identifying the specific activities needed to produce those work packages, determining their dependencies, and estimating durations. This directly feeds into creating the project schedule, which is the logical next step before cost estimation or risk identification.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Sequence the activities and develop the project schedule

    Why this is correct

    Following the creation of the Work Breakdown Structure (WBS), which decomposes project deliverables into manageable work packages and activities, the next logical step in predictive planning is to sequence these activities. This involves determining dependencies and relationships between tasks, which is a prerequisite for developing a realistic and detailed project schedule. Therefore, sequencing activities and subsequently developing the project schedule directly follows the WBS in the planning process flow.

  • Define the project scope statement

    Why it's wrong here

    Defining the project scope statement is a foundational planning process that occurs much earlier than activity sequencing. This critical document establishes the project's boundaries, deliverables, and acceptance criteria, serving as the basis from which the Work Breakdown Structure (WBS) is subsequently developed. Therefore, defining the scope statement precedes the WBS, rather than following it.

  • Identify risks

    Why it's wrong here

    Initial, comprehensive risk identification typically occurs after the project's scope, schedule, and cost baselines have been largely established. While risk management is an ongoing process, the formal identification of specific risks is more effective when there is a clear understanding of what needs to be done, by when, and for how much. Performing this step immediately after the WBS would be premature for a thorough risk analysis.

  • Estimate costs for each work package

    Why it's wrong here

    Estimating costs for each work package is a subsequent step in the planning process, generally performed after the project schedule has been developed. The schedule provides crucial information regarding activity durations, resource assignments, and sequencing, all of which directly influence the accuracy and detail of cost estimates. Without a developed schedule, cost estimates would lack the necessary foundational data for precision.

Go deeper

Related to this question

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.