Courseiva

PMP Practice Question: Business Environment: strategy and project benefits

You are managing a portfolio of projects. One project has a high probability of missing its deadline, which will impact the organization's strategic goals. What should you do first?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Analyze the impact on strategic goals and communicate with the sponsor and steering committee

The portfolio manager should analyze the situation and communicate the issue to stakeholders to align on corrective actions or reprioritization.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Add more resources to the project to try to meet the deadline

    Why it's wrong here

    Adding resources (e.g., people, equipment) to a struggling project without first understanding the root cause of the delay (e.g., scope creep, poor estimates, skill gaps) can lead to increased costs, communication overhead (Brooks's Law), and further delays. A thorough analysis is required before committing more investment, as simply increasing inputs does not guarantee improved outputs or adherence to the deadline.

  • Ignore the issue because it is only one project in the portfolio

    Why it's wrong here

    As a portfolio manager, ignoring the performance of any project, even a single one, is a significant oversight. Each project within a portfolio is specifically selected and authorized to contribute to overarching organizational strategic objectives. Ignoring a struggling project risks its failure, which directly jeopardizes the achievement of those strategic goals and the overall value delivery of the entire portfolio.

  • Analyze the impact on strategic goals and communicate with the sponsor and steering committee

    Why this is correct

    This is the most appropriate initial action for a portfolio manager. The primary role of portfolio management is to ensure continuous alignment with the organization's strategic objectives and maximize value. Therefore, understanding how a project's issue impacts those overarching goals is paramount. Communicating this analysis to the sponsor and steering committee enables informed, high-level decision-making regarding potential adjustments, re-prioritization, or corrective actions at the portfolio level.

  • Immediately cancel the project to reallocate resources

    Why it's wrong here

    Immediately canceling a project without proper analysis of its current status, potential for recovery, or impact on strategic objectives is a premature and potentially damaging decision. Such an action would waste previous investments, disrupt resource planning across the portfolio, and could alienate key stakeholders. A structured evaluation, impact assessment, and stakeholder consultation are essential before considering such a drastic measure.

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.