PMP Process — Managing Technical Aspects Practice Question

You are managing a project using a hybrid approach. The project has a fixed-price contract with a customer. Midway through, the customer requests a significant scope change that would increase the contract value. The change request is approved by the CCB. What must the project manager do NEXT?

⚠ Common exam trap

Many exam-takers confuse the order of actions after CCB approval, often jumping to 'update the contract' (Option C) or 'start work immediately' (Option B), forgetting that the project management plan and baselines must be formally updated and communicated first to maintain control over the project's performance measurement.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Update the project management plan and baselines, and communicate the approved change to all relevant stakeholders.

After a change is approved by the CCB, the project manager must first update the project management plan and baselines (scope, schedule, cost) to reflect the approved change, then communicate the change to all relevant stakeholders. This ensures that the project's performance measurement baselines are aligned with the new scope and cost, and that all stakeholders are aware of the updated plan before work begins. In a hybrid approach with a fixed-price contract, updating the contract is a separate procurement process that occurs after the baselines are updated and communicated.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Inform the team of the approved change and update the work packages accordingly.

    Why it's wrong here

    Informing the team and updating work packages immediately after approval, but before formal baseline updates, is premature and can lead to significant inconsistencies. Work packages are detailed components derived from the project management plan and baselines. Without first updating the authoritative project plan and baselines, the project's official record remains misaligned, potentially causing confusion, rework, or scope creep as the team executes against outdated foundational documents.

  • Proceed with the change immediately to avoid delays.

    Why it's wrong here

    Proceeding with an approved change immediately without first updating the project management plan and baselines bypasses critical control mechanisms. This action creates a discrepancy between the planned and actual project state, making it impossible to accurately measure performance, track progress, or justify future decisions. Such an approach undermines project governance, increases risks of scope creep, budget overruns, and schedule delays, and compromises the integrity of the project's formal documentation.

  • Update the contract with the new scope and cost, and then start the work.

    Why it's wrong here

    While an approved change might necessitate a contract amendment, directly updating the contract is typically a function performed by the procurement department, not the project manager. The project manager's primary responsibility, after an internal change approval, is to update the project management plan and baselines to reflect the new scope and cost. This internal documentation then serves as the basis for any necessary external contractual adjustments, which are subsequently managed through formal procurement processes.

  • Update the project management plan and baselines, and communicate the approved change to all relevant stakeholders.

    Why this is correct

    After a change request receives formal approval, the project manager's immediate and crucial responsibility is to integrate that approved change into the project management plan and its subsidiary baselines, such as scope, schedule, and cost. This ensures all project documentation accurately reflects the revised project direction. Following this essential update, communicating the approved change and its implications to all relevant stakeholders is vital for maintaining transparency, aligning expectations, and ensuring everyone operates from the most current and authoritative project information.

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.