Courseiva
Process — Managing Technical AspectseasyMultiple SelectObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

You are closing a project that has delivered all scope successfully. Which THREE activities are essential to complete during the project closure phase?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Obtain formal acceptance of the final deliverables from the customer.

Project closure involves formal acceptance, archiving, and releasing resources. Lessons learned are documented throughout the project but are also reviewed at closure. These are key closure activities per PMI.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Conduct a performance review for each team member.

    Why it's wrong here

    While individual performance assessments might inform future assignments or HR records, formal performance reviews are typically an organizational HR function, not a direct process within the Project Closure process group as defined by the PMBOK Guide. Project closure focuses on administrative closure, contractual closure, and transitioning the final product, service, or result. The project manager's role is to provide input to organizational performance management systems, not to conduct the reviews themselves.

  • Obtain formal acceptance of the final deliverables from the customer.

    Why this is correct

    This is a critical step in the Close Project or Phase process, specifically related to validating the scope. Obtaining formal acceptance from the customer or sponsor signifies their agreement that the project's final deliverables meet all specified requirements and that the project objectives have been achieved. This formal sign-off is essential for contractual closure and for confirming that the project has successfully delivered its intended product, service, or result.

  • Release project resources and communicate their reassignment.

    Why this is correct

    Releasing project resources, including team members, equipment, and facilities, is a key administrative closure activity. This involves formally transitioning team members back to their functional managers or to new projects, ensuring proper handover of responsibilities and knowledge. Communicating their reassignment is crucial for organizational planning and efficient resource utilization, preventing resources from remaining idle and ensuring a smooth transition out of the project.

  • Archive project documents and update the organizational process assets.

    Why this is correct

    Archiving all relevant project documentation, such as project plans, performance reports, and lessons learned, is a fundamental administrative closure activity. Concurrently, updating organizational process assets (OPAs) with new knowledge gained, like updated policies, procedures, and historical information, ensures that the organization can leverage this experience for future projects. This systematic knowledge transfer is vital for continuous improvement and enhancing organizational maturity.

  • Update the project schedule with actual finish dates.

    Why it's wrong here

    While tracking actual finish dates is part of monitoring and controlling project work throughout execution, the primary activity during project closure is not to update the schedule itself. By the time a project is closing, all work should be complete, and the schedule's utility for active management has diminished. Any final schedule data would be incorporated into the final project report and archived, rather than actively "updating" a live schedule document.

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.