Question 249 of 892

Quick Answer

The correct action is to assess the impact on the sprint goal and inform the product owner and stakeholders. This is because Scrum is built on transparency and empirical process control; when a vendor delay in a Scrum sprint occurs, the immediate priority is to understand how the impediment affects the sprint’s defined objective before escalating. On the PMP exam, this scenario tests your grasp of the Agile principle that the project manager acts as a servant leader, facilitating communication rather than unilaterally rescheduling work. A common trap is to jump into problem-solving—like finding a substitute vendor or extending the sprint—without first evaluating the impact on the sprint goal. Remember the mnemonic “A.I.R.”: Assess the impact, Inform the product owner, and update the Risk register. This sequence ensures you maintain stakeholder trust and keep the sprint backlog aligned with the product vision.

PMP Practice Question: Business Environment: strategy and project benefits

This PMP practice question tests your understanding of business environment: strategy and project benefits. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Your project is using Scrum. During the daily standup, a team member mentions that a key vendor will be unable to deliver a critical component on time, which will delay the next sprint. What is the best action to take?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "best"

    Why it matters: Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.

Question 1easymultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Assess the impact on the sprint goal and inform the product owner and stakeholders

The project manager should first assess the impact on the sprint and project, then communicate the issue to relevant stakeholders and update the risk register.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Ask the team to work overtime to compensate for the delay

    Why it's wrong here

    Working overtime may not be sustainable and does not address the vendor issue.

  • Assess the impact on the sprint goal and inform the product owner and stakeholders

    Why this is correct

    Assessing impact and communicating with stakeholders is the correct proactive approach.

    Clue confirmation

    The clue word "best" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Escalate to the vendor's management immediately

    Why it's wrong here

    While escalation may be needed later, the first step is to assess internal impact and communicate.

  • Immediately remove the component from the sprint backlog and continue with other work

    Why it's wrong here

    This action does not address the root cause or communicate the issue to stakeholders.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Business Environment: strategy and project benefits — This question tests Business Environment: strategy and project benefits — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Assess the impact on the sprint goal and inform the product owner and stakeholders — The project manager should first assess the impact on the sprint and project, then communicate the issue to relevant stakeholders and update the risk register.

What should I do if I get this PMP question wrong?

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Are there clue words in this question I should notice?

Yes — watch for: "best". Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A project manager discovers that a key vendor will be unable to deliver a critical component on time, which will delay the project. The contract includes penalties for late delivery. What should the project manager do first?

easy
  • A.Assess the impact on the project schedule and explore alternative solutions.
  • B.Inform the sponsor and wait for instructions.
  • C.Immediately invoke the penalty clause to incentivize the vendor.
  • D.Terminate the contract and find a new vendor.

Why A: The first step is to assess the impact and explore alternatives, then formally communicate with the vendor. This aligns with risk management and procurement. Option A is premature without analysis. Option C is reactive. Option D is extreme and may damage the relationship.

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.