Question 196 of 892
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is that costs are higher than planned for the work performed. This is the most likely reason because cost variance analysis in project management compares earned value (EV) to actual cost (AC), and here AC of $115,000 exceeds EV of $100,000, producing a negative cost variance of -$15,000. Since the project is 15% over budget at the midpoint, the actual expenditures have outpaced the value of work completed, confirming a cost overrun rather than a schedule or scope issue. On the PMP exam, this scenario tests your ability to interpret EVM metrics and distinguish between cost variance (CV = EV - AC) and schedule variance (SV = EV - PV); a common trap is confusing a negative CV with being behind schedule, but here the schedule is also behind since EV is less than PV. A useful memory tip is to remember that cost variance is about the budget spent versus work done, so if AC is greater than EV, you are spending more for less—think “AC > EV = cost overdrive.”

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

You are managing a project that is 15% over budget at the midpoint. The earned value (EV) is $100,000, actual cost (AC) is $115,000, and planned value (PV) is $110,000. What is the most likely reason for the cost variance?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "most likely"

    Why it matters: Probability qualifier — the question wants the most probable cause or outcome, not a guaranteed one. Eliminate low-probability options.

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Costs are higher than planned for the work performed

Option B is correct because AC > EV and AC > PV indicates cost overrun. Option A is wrong because EV is less than PV, indicating behind schedule, not ahead. Option C is wrong because the project is behind schedule, not ahead. Option D is wrong because scope increase would likely increase EV as well.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Costs are higher than planned for the work performed

    Why this is correct

    AC > EV shows cost overrun.

    Clue confirmation

    The clue word "most likely" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • The project is ahead of schedule

    Why it's wrong here

    PV > EV indicates behind schedule.

  • The project is under budget

    Why it's wrong here

    AC > EV shows over budget.

  • The scope was increased without adjusting the budget

    Why it's wrong here

    Scope increase would likely increase EV proportionally.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Trap categories for this question

  • Command / output trap

    AC > EV shows over budget.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Costs are higher than planned for the work performed — Option B is correct because AC > EV and AC > PV indicates cost overrun. Option A is wrong because EV is less than PV, indicating behind schedule, not ahead. Option C is wrong because the project is behind schedule, not ahead. Option D is wrong because scope increase would likely increase EV as well.

What should I do if I get this PMP question wrong?

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Are there clue words in this question I should notice?

Yes — watch for: "most likely". Probability qualifier — the question wants the most probable cause or outcome, not a guaranteed one. Eliminate low-probability options.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Your project is running 15% over budget at the midpoint. The cost variance is due to higher-than-expected material costs. What is the BEST action?

medium
  • A.Reduce the quality of deliverables to cut costs
  • B.Analyze the variance and implement corrective actions such as reducing scope or using cheaper materials
  • C.Request additional budget from the sponsor
  • D.Inform the sponsor of the overrun and wait for instructions

Why B: The PM should analyze the variance, determine root cause, and develop corrective actions, then communicate to stakeholders.

Variation 2. You are managing a project that is running 15% over budget at the midpoint. The variance is due to higher-than-expected material costs. The sponsor is concerned about cost overruns. What should you do FIRST?

medium
  • A.Ask the team to find cheaper alternatives for materials immediately
  • B.Reduce the project scope to bring costs back in line with the budget
  • C.Analyze the cost variance to determine the root cause and update the EAC
  • D.Request additional budget from the sponsor to cover the overrun

Why C: The PM should first analyze the root cause of the cost variance and determine if the trend is likely to continue. Based on this analysis, the PM can develop a revised estimate at completion (EAC) and communicate it to the sponsor. Simply asking for more budget or reducing scope without analysis is premature.

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.