PRINCE2F PRINCE2 Processes Practice Question
Who is responsible for producing the Highlight Report during the Controlling a Stage process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Manager
The Project Manager produces the Highlight Report during Controlling a Stage to inform the Project Board about progress. Team Managers produce Checkpoint Reports. Project Support may assist but not produce it. The Senior User does not produce it.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Senior User
Why it's wrong here
The Senior User is a member of the Project Board and receives Highlight Reports but does not produce them.
- ✗
Team Manager
Why it's wrong here
Team Managers produce Checkpoint Reports, not Highlight Reports.
- ✗
Project Support
Why it's wrong here
Project Support may assist with documentation but the PM produces the Highlight Report.
- ✓
Project Manager
Why this is correct
The Project Manager produces Highlight Reports during Controlling a Stage.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.