Which THREE of the following are PRINCE2 practices (themes)?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Risk

In PRINCE2, the seven themes (now called practices in PRINCE2 2017) describe aspects of project management that must be addressed continually, and Risk (B), Quality (D), and Business Case (E) are three of them. Risk (B) is correct because PRINCE2 requires a Risk theme/practice covering risk identification, assessment, and response throughout the project. Quality (D) is correct because the Quality theme/practice defines how the project will verify that products meet requirements and achieve fitness for purpose. Business Case (E) is correct because the Business Case theme/practice ensures the project remains desirable, viable, and achievable, justifying continued investment. Waterfall (A) is not a PRINCE2 theme but a sequential development approach, and Sprint Planning (C) is a Scrum event, not a PRINCE2 practice.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Waterfall

    Why it's wrong here

    Waterfall is a sequential delivery lifecycle, not one of the seven PRINCE2 practices such as business case, organisation, quality, plans, risk, change and progress. It is tempting because PRINCE2's process model is often delivered sequentially, yet lifecycle choice sits under tailoring rather than the practices themselves.

  • ✓

    Risk

    Why this is correct

    Risk is one of the seven PRINCE2 practices, alongside business case, organisation, plans, quality, change and progress. It satisfies the stem's requirement by being a recognised practice, governing how the project team identifies, assesses and controls uncertainty throughout each stage of the project lifecycle.

  • ✗

    Sprint Planning

    Why it's wrong here

    Sprint Planning belongs to Scrum, not PRINCE2's seven practices (business case, organisation, quality, plans, risk, change, progress). It is tempting because PRINCE2 can be tailored alongside agile delivery, but Sprint Planning remains a Scrum event and is never a PRINCE2 practice.

  • ✓

    Quality

    Why this is correct

    Quality is a PRINCE2 practice, covering quality planning, quality control and the definition of acceptance criteria and quality tolerances. It ensures products meet their requirements and that verification responsibilities are assigned within the project's organisation.

  • ✓

    Business Case

    Why this is correct

    Business Case is one of the seven PRINCE2 practices, providing the viability justification that drives decision-making throughout the project. It satisfies the stem's requirement by being a recognised practice, alongside Organisation, Plans, Quality, Risk, Change and Progress.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which TWO of the following are PRINCE2 practices (themes)?

medium
  • A.Managing a Stage Boundary
  • B.Directing a Project
  • C.Starting Up a Project
  • ✓ D.Risk
  • ✓ E.Business Case

Why D: In PRINCE2, the seven themes (now called practices in PRINCE2 2017/2023) include Risk (D) and Business Case (E); these are ongoing aspects applied throughout the project to ensure it remains viable and controlled. Risk (D) is correct because it is one of the seven themes/practices, covering the identification, assessment, and control of uncertainty. Business Case (E) is correct because it is also one of the seven themes/practices, ensuring the project remains desirable, viable, and achievable. The other options are processes, not themes/practices: Managing a Stage Boundary (A), Directing a Project (B), and Starting Up a Project (C) are all part of the PRINCE2 process model.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.