Courseiva

PRINCE2F · topic practice

PRINCE2 Practices practice questions

This domain covers how PRINCE2 organizes work into controllable stages and manages change: Business Case, Organization, Plans, Progress, Change, and Quality practices. Questions test definitions, role responsibilities, and document purposes, often by contrasting similar artifacts (Request for Change vs Off-specification) or asking which role decides what within tolerance.

Courseiva uses original exam-style practice questions designed for learning and revision. The goal is to understand the concepts, recognise exam patterns, and improve through explanations — not memorise copied exam dumps.

Editorial oversight:Johnson Ajibi· MSc IT Security, IEEE Senior Member
20 questionsDomain: PRINCE2 Practices

What the exam tests

What to know about PRINCE2 Practices

Be able to state the purpose of each progress report and change artifact, and identify which role holds which decision authority. The single most important thing: know that change approval authority can be delegated to a Change Authority within defined tolerances, not assumed by the Project Manager.

Purpose of Checkpoint, Highlight, and End Stage Reports within Progress practice

Difference between a Request for Change and an Off-specification in Change practice

Delegation of change authority within agreed tolerances to a Change Authority

Purpose of the Business Case and its ownership by the Executive across stages

Watch out for

Common PRINCE2 Practices exam traps

  • ▸Confusing a Request for Change (proposed change) with an Off-specification (something not yet delivered to agreed specification).
  • ▸Assuming the Project Manager approves all changes; authority may be delegated to a Change Authority within set limits.
  • ▸Treating the Business Case as a one-off document rather than something reviewed and updated at each stage boundary.

Practice set

PRINCE2 Practices questions

20 questions · select your answer, then reveal the explanation

In a project using PRINCE2, the project board is reviewing the End Stage Report. They notice that the actual costs are significantly lower than planned, but the scope is complete. What should the project board do?

A project manager is creating the project product description. Which practice does this document belong to?

Which THREE elements are part of the PRINCE2 Quality practice?

Based on the exhibit, what is the current risk exposure of risk R1?

Exhibit

Refer to the exhibit.

Exhibit:
Risk Register:
  Risk ID: R1
  Risk Type: Threat
  Risk Description: Key supplier may go out of business
  Probability: Low
  Impact: High
  Risk Owner: Project Manager
  Proximity: Within next stage
  Risk Response: Mitigate - Identify alternative suppliers

A project manager is reviewing the business case for a new product development project. The project board has expressed concern that the benefits may not be realized as planned. Which management product should the project manager update to address this concern?

A project manager is defining the project's products in the Product Breakdown Structure. A key stakeholder disagrees with the inclusion of a certain product, claiming it is not needed. The project manager believes the product is essential to meet the user requirements. What is the best course of action according to PRINCE2 practices?

A project is in the Initiating a Project process. The project manager is creating the Risk Management Approach. Which of the following should be included in this approach?

Which TWO statements about the PRINCE2 practice 'Organizing' are correct?

During a quality review, it is discovered that the acceptance criterion 'The system shall be compatible with Windows 10 and macOS' has been classified as 'Should' (i.e., a desirable but not essential criterion). Which action should be taken?

Exhibit

Refer to the exhibit.

Project Product: New Customer Relationship Management (CRM) System

Acceptance Criteria:
- The system shall support up to 10,000 concurrent users (Must)
- The average response time shall be less than 2 seconds (Must)
- The system shall be compatible with Windows 10 and macOS (Should)
- The user interface shall be customizable (Could)

Exhibit: Extract from the Project Product Description

A project to upgrade the IT infrastructure of a medium-sized company is in the Initiating a Project process. The project manager has created the Business Case, which shows a net present value (NPV) of £150,000 and an internal rate of return (IRR) of 12%. The project board's executive is concerned that the project may not deliver the expected benefits because the market demand for the new infrastructure is uncertain. The project manager is now preparing the Project Plan. What should the project manager do next?

Drag and drop the steps to create a PRINCE2 project plan into the correct order.

Drag or tap steps into the slots.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Match each level of management in PRINCE2 to its description.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Provides direction and resources for the project.

Accountable for the project's success and makes key decisions.

Responsible for day-to-day management and control.

Responsible for delivering one or more products within a work package.

Who is responsible for maintaining the Business Case throughout the project?

Question 14mediummultiple choice
Read the full PRINCE2 Practices explanation →

Which document is the key output of the Initiating a Project process?

Question 15mediummultiple choice
Read the full PRINCE2 Practices explanation →

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

Question 16mediummultiple choice
Read the full PRINCE2 Practices explanation →

What is the purpose of the Managing a Stage Boundary process?

What is the difference between a Request for Change and an Off-specification?

Which TWO of the following are types of issue in PRINCE2?

Who is responsible for maintaining the Business Case throughout the project?

Question 20mediummultiple choice
Read the full PRINCE2 Practices explanation →

Which process is triggered when a stage tolerance is forecast to be exceeded?

Free account

Track your progress over time

Create a free account to save your results and see which topics improve across sessions.

Focused PRINCE2 Practices sessions

Start a PRINCE2 Practices only practice session

Every question in these sessions is drawn from the PRINCE2 Practices domain — nothing else.

Related practice questions

Related PRINCE2F topic practice pages

Move into related areas when this topic feels solid.

Frequently asked questions

What does the PRINCE2F exam test about PRINCE2 Practices?
Be able to state the purpose of each progress report and change artifact, and identify which role holds which decision authority. The single most important thing: know that change approval authority can be delegated to a Change Authority within defined tolerances, not assumed by the Project Manager.
How should I use these practice questions?
Select your answer before revealing the explanation. Then read why each option is right or wrong — this active recall approach builds retention far faster than re-reading notes.
Can I practise just PRINCE2 Practices questions in a focused session?
Yes — the session launcher on this page draws every question from the PRINCE2 Practices domain. Use a 10-question session first to gauge your baseline, then move to 20 or 30 once the weak spots are clear.
Where can I practise other PRINCE2F topics?
Use the topic links above to move to related areas, or go back to the PRINCE2F question bank to see all topics.
Are these real exam questions or dumps?
These are original practice questions written to test the same concepts the PRINCE2F exam covers. They are not copied from any real exam or dump site.