CCNA Overview of PRINCE2 and Principles Questions

14 questions · Overview of PRINCE2 and Principles · All types, answers revealed

1
Matchingmedium

Match each PRINCE2 principle to its description.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Ensure there is a justifiable reason to start and continue the project.

Seek lessons from previous and current projects.

Clearly define roles and responsibilities for all involved.

Plan, monitor, and control the project on a stage-by-stage basis.

Define tolerances for each objective and delegate authority within those limits.

Why these pairings

The seven PRINCE2 principles are these five plus 'Focus on Products' and 'Tailor to Suit the Project Environment'.

2
MCQmedium

A project to build a new bridge is underway. The project board has decided to use a stage plan for the next stage rather than a detailed Gantt chart for the entire project. This approach aligns with which PRINCE2 principle?

A.Continued business justification
B.Learn from experience
C.Focus on products
D.Manage by stages
AnswerD

This principle involves planning in stages.

Why this answer

The decision to use a stage plan for the next stage rather than a detailed Gantt chart for the entire project directly reflects the 'Manage by stages' principle. This principle requires that the project board only plans in detail for the immediate next stage, while higher-level plans cover the remainder of the project, enabling control and flexibility.

Exam trap

The trap here is that candidates may confuse 'Manage by stages' with 'Focus on products' or 'Learn from experience', but the key differentiator is that stage planning is about controlling the project in manageable chunks, not about product definition or lessons learned.

How to eliminate wrong answers

Option A is wrong because 'Continued business justification' focuses on ensuring the project remains viable and aligned with business objectives, not on the level of planning detail. Option B is wrong because 'Learn from experience' involves using lessons from previous projects or stages, not the decision to plan stage-by-stage. Option C is wrong because 'Focus on products' emphasizes defining and delivering products, not the planning approach of using stage plans.

3
MCQmedium

Refer to the exhibit. Which principle is missing from the configuration?

A.Manage by stages
B.Focus on products
C.Manage by exception
D.All principles are applied
AnswerA

Manage by stages is set to false, indicating it is not applied.

Why this answer

The PRINCE2 principle 'Manage by stages' is missing from the exhibit because the configuration lists only 'Continued business justification,' 'Learn from experience,' 'Roles and responsibilities,' 'Manage by exception,' 'Focus on products,' and 'Tailor to suit the project environment.' The seven PRINCE2 principles are all required, and 'Manage by stages' is the one omitted. Without it, the project lacks the mandatory planning and control mechanism that divides the project into discrete management stages, each with its own plan and review points.

Exam trap

PeopleCert often tests the exact list of the seven PRINCE2 principles, and the trap here is that candidates may overlook 'Manage by stages' because they confuse it with 'Manage by exception' or assume that 'Focus on products' covers the missing principle, when in fact each principle is distinct and all seven must be present.

How to eliminate wrong answers

Option B is wrong because 'Focus on products' is explicitly listed in the exhibit, so it is not missing. Option C is wrong because 'Manage by exception' is also explicitly listed in the exhibit, so it is not missing. Option D is wrong because the exhibit clearly omits one of the seven PRINCE2 principles ('Manage by stages'), so not all principles are applied.

4
Multi-Selectmedium

Which TWO of the following are PRINCE2 principles?

Select 2 answers
A.Risk management
B.Configuration management
C.Continued business justification
D.Waterfall methodology
E.Manage by stages
AnswersC, E

This is a PRINCE2 principle.

Why this answer

Continued business justification is a core PRINCE2 principle that requires the business case to remain viable throughout the project lifecycle. This principle ensures that the project is not started without a clear justification and that this justification is reviewed and updated at key decision points, such as stage boundaries. It directly supports the PRINCE2 focus on ongoing viability rather than a one-time approval.

Exam trap

PeopleCert often tests the distinction between principles and themes, so the trap here is confusing a theme (like risk management or configuration management) with a principle, leading candidates to select options that are valid PRINCE2 components but not principles.

5
Drag & Dropmedium

Drag and drop the steps of the PRINCE2 Starting up a Project process into the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order

Why this order

The Starting up a Project process ensures that the prerequisites for initiating a project are in place, starting with appointing key roles, then learning from past projects, building the team, developing the outline business case, and finally selecting the approach.

6
MCQhard

A project manager notices that the project's product descriptions are being created after the products have already been developed. Which PRINCE2 principle is being ignored?

A.Learn from experience
B.Focus on products
C.Tailor to suit the project environment
D.Manage by stages
AnswerB

Products must be defined before development.

Why this answer

The 'Focus on Products' principle requires that a project defines and agrees on product descriptions (including quality criteria) before development begins, ensuring that all stakeholders have a shared understanding of what will be delivered. Creating product descriptions after development violates this principle because it undermines the definition of scope, quality expectations, and acceptance criteria upfront, leading to potential rework and misalignment.

Exam trap

PeopleCert often tests the distinction between 'Focus on products' and 'Manage by stages' by making candidates confuse the timing of product definition with the stage-gate approval process, but the trap here is that candidates may think 'Manage by stages' addresses when products are built, whereas it actually controls the sequence of management stages, not the order of product description creation.

How to eliminate wrong answers

Option A is wrong because 'Learn from experience' involves using lessons from previous projects to improve current performance, not the timing of product description creation. Option C is wrong because 'Tailor to suit the project environment' refers to adapting PRINCE2 processes to the project's context, not to the order of product definition versus development. Option D is wrong because 'Manage by stages' concerns planning and controlling the project in manageable chunks, not the requirement to define products before building them.

7
MCQhard

You are the project manager for a large-scale IT infrastructure project for a multinational corporation. The project involves deploying new servers across 20 countries, with a budget of $5 million and a timeline of 18 months. The project has been running for 6 months and is currently in its second stage. The project board consists of the executive, senior user, and senior supplier. Recently, the senior user has been raising concerns that the project is not delivering the expected benefits, and the business case may no longer be viable due to changes in market conditions. The senior supplier argues that the project should continue because significant resources have already been invested. The executive is undecided. As the project manager, you need to advise the project board on the best course of action based on PRINCE2 principles. Which of the following should you recommend?

A.Postpone the decision until the end of the current stage to conduct a full review.
B.Request the project board to review and update the business case immediately. If it is no longer viable, recommend stopping the project.
C.Tailor the continued business justification principle to allow the project to continue due to its strategic importance.
D.Continue with the project as planned because significant investment has already been made.
AnswerB

This aligns with the continued business justification principle.

Why this answer

B is correct because PRINCE2's continued business justification principle requires that the business case remain viable throughout the project. As project manager, you must escalate to the project board for an immediate review when the senior user raises concerns about benefits and market changes. If the business case is no longer viable, the project should be stopped to avoid further waste of resources, regardless of sunk costs.

Exam trap

The trap here is that candidates confuse the 'manage by stages' principle with delaying decisions, or they incorrectly believe that tailoring can override a fundamental principle like continued business justification.

How to eliminate wrong answers

Option A is wrong because postponing the decision until the end of the stage violates the continued business justification principle, which demands immediate reassessment when viability is questioned. Option C is wrong because tailoring cannot override a core principle; the continued business justification principle must be upheld, not tailored away to allow an unviable project to continue. Option D is wrong because continuing due to significant investment already made is a classic sunk cost fallacy, which PRINCE2 explicitly rejects in favor of ongoing business justification.

8
Multi-Selecthard

Which THREE of the following are PRINCE2 principles?

Select 3 answers
A.Tailor to suit the project environment
B.Plans
C.Focus on products
D.Business Case
E.Learn from experience
AnswersA, C, E

This is a PRINCE2 principle.

Why this answer

Option A is correct because 'Tailor to suit the project environment' is one of the seven PRINCE2 principles. This principle requires that the method be adapted to the specific context of the project, including its size, complexity, importance, capability, and risk, ensuring that PRINCE2 is applied appropriately without unnecessary bureaucracy.

Exam trap

The trap here is that candidates often confuse PRINCE2 themes (like Plans and Business Case) with principles, because both are core components of the method, but principles are the mandatory obligations that underpin the entire framework, whereas themes are knowledge areas that are applied through the processes.

9
MCQhard

During a project, a key stakeholder raises a concern that the project scope has expanded significantly without formal approval. The project manager realizes that changes have been implemented informally. Which PRINCE2 principle has been violated?

A.Defined roles and responsibilities
B.Continued business justification
C.Manage by stages
D.Learn from experience
AnswerC

Changes must be managed within stage boundaries.

Why this answer

The scenario describes scope changes being implemented without formal approval, which violates the 'Manage by stages' principle. PRINCE2 requires that a project be planned, monitored, and controlled on a stage-by-stage basis, with each stage ending in a formal review and approval before proceeding. Implementing changes informally bypasses stage boundaries and the associated management controls, directly breaking this principle.

Exam trap

The trap here is that candidates confuse 'Manage by stages' with 'Defined roles and responsibilities' because they think the project manager should have formally approved the change, but the principle violated is specifically about stage-based control, not role definition.

How to eliminate wrong answers

Option A is wrong because 'Defined roles and responsibilities' focuses on clear assignment of project roles, not on the control of scope changes or stage boundaries. Option B is wrong because 'Continued business justification' ensures the project remains viable, but the issue here is about unauthorized scope changes, not a lack of business case validation. Option D is wrong because 'Learn from experience' involves capturing lessons throughout the project, but the core violation is the lack of formal stage-gate control over changes, not the failure to document lessons.

10
MCQeasy

A project team is working on a complex infrastructure project. The project manager wants to ensure that the project is tailored appropriately. According to PRINCE2, which principle addresses the need to adapt PRINCE2 to the project's specific context?

A.Continued business justification
B.Focus on products
C.Manage by stages
D.Tailor to suit the project environment
AnswerD

This principle ensures PRINCE2 is adapted appropriately.

Why this answer

The 'Tailor to suit the project environment' principle directly addresses the need to adapt PRINCE2 to the specific context of the project, including its size, complexity, importance, capability, and risk. For a complex infrastructure project, this means adjusting management products, roles, and processes (e.g., simplifying the Business Case or using a more detailed Risk Register) to fit the project's unique technical and organizational environment, ensuring the method remains effective without being overly burdensome.

Exam trap

PeopleCert often tests the distinction between the 'Tailor to suit the project environment' principle and the 'Manage by stages' principle, as candidates may confuse adapting the method's processes with the structural decision to break the project into stages.

How to eliminate wrong answers

Option A is wrong because 'Continued business justification' ensures the project remains viable and aligned with business objectives, but it does not address the adaptation of PRINCE2 to the project's specific context. Option B is wrong because 'Focus on products' emphasizes defining and delivering products with agreed quality criteria, not tailoring the method itself. Option C is wrong because 'Manage by stages' involves planning, monitoring, and controlling the project in stages, which is a structural element of PRINCE2, not a principle about adapting the method to the project environment.

11
MCQmedium

A project manager is reviewing the business case for a new software development project. The project is expected to generate significant revenue, but the initial investment is high. According to PRINCE2, which principle is MOST directly being applied when the project manager ensures that the business case remains viable throughout the project?

A.Manage by stages
B.Learn from experience
C.Continued business justification
D.Tailor to suit the project environment
AnswerC

This principle ensures the business case is kept under review.

Why this answer

The PRINCE2 principle of Continued Business Justification requires that the business case, which documents the project's justification, is reviewed and updated at key decision points (e.g., stage boundaries) to ensure the project remains viable. In this scenario, the project manager is actively verifying that the high initial investment is still justified by the expected revenue, directly applying this principle to avoid proceeding with an unviable project.

Exam trap

PeopleCert often tests the distinction between 'Continued Business Justification' and 'Manage by Stages,' where candidates mistakenly think stage boundaries are for business case review, but the principle itself is about ongoing viability, not the mechanism of stage management.

How to eliminate wrong answers

Option A is wrong because Manage by Stages is a principle about dividing the project into management stages for control, not about continuously validating the business case. Option B is wrong because Learn from Experience focuses on capturing and applying lessons from previous projects, not on ongoing business justification. Option D is wrong because Tailor to Suit the Project Environment is about adapting PRINCE2 processes to the project's context, not about ensuring the business case remains viable.

12
Matchingmedium

Match each PRINCE2 principle to its description.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

A project must have a justifiable reason to start and remain viable.

Lessons are sought and applied throughout the project.

Clear roles for project team members are defined and agreed.

The project is planned, monitored, and controlled on a stage-by-stage basis.

The project focuses on the delivery of products, not activities.

Why these pairings

These are five of the seven PRINCE2 principles.

13
MCQeasy

Refer to the exhibit. Which principle is not being applied in the project?

A.Manage by stages
B.Tailor to suit the project environment
C.Learn from experience
D.Focus on products
AnswerC

The output shows Learn from Experience: NO.

Why this answer

The principle 'Learn from experience' is not being applied because the project team is repeating the same mistakes from previous projects without reviewing lessons learned logs or incorporating feedback. PRINCE2 requires continuous learning throughout the project lifecycle, but the exhibit shows no evidence of lessons being documented or used to improve current practices.

Exam trap

PeopleCert often tests the misconception that 'Learn from experience' only applies at the end of a project, when in fact PRINCE2 requires continuous learning from the start through to closure.

How to eliminate wrong answers

Option A is wrong because 'Manage by stages' is being applied — the project is divided into distinct stages with stage boundaries and approval points visible in the exhibit. Option B is wrong because 'Tailor to suit the project environment' is being applied — the project management approach has been adapted to fit the specific technology stack and organizational context shown. Option D is wrong because 'Focus on products' is being applied — the project has clearly defined product descriptions, quality criteria, and acceptance criteria for deliverables.

14
Drag & Dropmedium

Drag and drop the steps to apply the PRINCE2 quality review technique into the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order

Why this order

Quality review: plan, distribute, prepare, meet, and follow up.

Ready to test yourself?

Try a timed practice session using only Overview of PRINCE2 and Principles questions.