A project team is distributed across three time zones, causing communication delays. The project manager wants to apply the 'manage by stages' principle effectively. What should the project manager do first?
Trap 1: Increase the number of management stages to allow more frequent…
Adding stages alters the number of control points but not the underlying delegation of authority and tolerances that 'manage by stages' requires; the principle concerns defining and authorising each stage, not multiplying them. More stages suit long, high-risk projects needing tighter review, not a communication-delay problem.
Trap 2: Update the communication management approach to include…
Communication delays are a delivery concern, not a stage-boundary control; the communication management approach governs channels, not the delegation of authority that 'manage by stages' requires. It would be correct when planning how distributed teams exchange information, but here the principle demands defining stage boundaries and tolerances first.
Trap 3: Implement daily stand-up meetings at a time that is convenient for…
Scheduling stand-ups addresses daily coordination, not the stage-boundary and tolerance structure that 'manage by stages' governs. Stand-ups suit agile delivery cadence, but this principle requires the Project Board to authorise work stage by stage, with defined tolerances, before any meeting format is chosen.
- A
Increase the number of management stages to allow more frequent checkpoints
Why it fails: Adding stages alters the number of control points but not the underlying delegation of authority and tolerances that 'manage by stages' requires; the principle concerns defining and authorising each stage, not multiplying them. More stages suit long, high-risk projects needing tighter review, not a communication-delay problem.
- B
Plan the next management stage with clear communication milestones that account for time zone differences
Splitting the work into management stages gives the project manager a defined boundary at which to plan communication milestones around each team's working hours, directly addressing the time-zone delays. Planning the next stage first converts the 'manage by stages' principle into concrete, time-zone-aware checkpoints.
- C
Update the communication management approach to include asynchronous updates
Why it fails: Communication delays are a delivery concern, not a stage-boundary control; the communication management approach governs channels, not the delegation of authority that 'manage by stages' requires. It would be correct when planning how distributed teams exchange information, but here the principle demands defining stage boundaries and tolerances first.
- D
Implement daily stand-up meetings at a time that is convenient for the majority
Why it fails: Scheduling stand-ups addresses daily coordination, not the stage-boundary and tolerance structure that 'manage by stages' governs. Stand-ups suit agile delivery cadence, but this principle requires the Project Board to authorise work stage by stage, with defined tolerances, before any meeting format is chosen.