Overview of PRINCE2 and Principles practice questions

This domain covers the seven PRINCE2 principles and the structure of the method: principles, themes, processes, and the project environment. Questions test whether you can identify which principle applies to a scenario, recognise a principle being violated, and understand that principles are mandatory and never tailored away.

Courseiva uses original exam-style practice questions designed for learning and revision. The goal is to understand the concepts, recognise exam patterns, and improve through explanations — not memorise copied exam dumps.

Editorial oversight:Johnson Ajibi· MSc IT Security, IEEE Senior Member
20 questionsDomain: Overview of PRINCE2 and Principles

What the exam tests

What to know about Overview of PRINCE2 and Principles

Be able to match a scenario to the correct PRINCE2 principle and spot which principle is being ignored. The single most important point: all seven principles are mandatory and cannot be tailored away, only how they are applied is tailored.

The seven principles: continued business justification, learn from experience, defined roles and responsibilities, manage by stages, manage by exception, focus on products, tailor to suit the project environment.

The four integrated elements of PRINCE2: principles, themes, processes, and tailoring to the project environment.

Continued business justification and the business case as the driver for starting, continuing, and stopping a project.

Manage by exception using tolerances for time, cost, scope, quality, risk, and benefit delegated from the project board.

Watch out for

Common Overview of PRINCE2 and Principles exam traps

  • ▸Treating the seven principles as optional guidance that can be tailored out; PRINCE2 principles are mandatory and must always be applied.
  • ▸Confusing principles with themes or processes, for example naming 'business case' or 'starting up a project' as a principle.
  • ▸Assuming manage by exception removes board control; the board still sets tolerances and receives exception reports when they are forecast to be breached.

Practice set

Overview of PRINCE2 and Principles questions

20 questions · select your answer, then reveal the explanation

Refer to the exhibit. Which principle is not being applied in the project?

Network Topology
$ pr2 check-principlesproject myprojectRefer to the exhibit.PRINCE2 CLI Output:Status: COMPLIANTPrinciples:1. Continued Business Justification: YES2. Learn from Experience: NO4. Manage by Stages: YES5. Manage by Exception: YES6. Focus on Products: YES

Match each PRINCE2 principle to its description.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Ensure there is a justifiable reason to start and continue the project.

Seek lessons from previous and current projects.

Clearly define roles and responsibilities for all involved.

Plan, monitor, and control the project on a stage-by-stage basis.

Define tolerances for each objective and delegate authority within those limits.

Match each PRINCE2 principle to its description.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

A project must have a justifiable reason to start and remain viable.

Lessons are sought and applied throughout the project.

Clear roles for project team members are defined and agreed.

The project is planned, monitored, and controlled on a stage-by-stage basis.

The project focuses on the delivery of products, not activities.

A project manager is leading a project to implement a new CRM system. During a stage boundary, the project board asks for evidence that the project is being managed by exception. The project manager has defined tolerances for time and cost but has not defined tolerances for scope or quality. Which PRINCE2 principle is being violated, and what is the consequence?

A PRINCE2 project manager for a marketing campaign is preparing the Project Initiation Documentation. The Project Board has asked how the project will ensure that it remains aligned with the corporate strategy and that decision-makers have the necessary information. Which PRINCE2 principle should the project manager emphasize to address this concern?

A project manager is reviewing the PRINCE2 principles with the project team to ensure they are applied consistently. The team discusses how to apply the principle 'learn from experience' throughout the project. Which TWO of the following actions best demonstrate the application of the 'learn from experience' principle? (Choose two.)

A programme manager is reviewing a project that has just entered the 'Initiating a Project' process. The project manager has produced a detailed business case, but the programme manager notes that the business case does not explicitly state what would happen if the project were stopped. Which PRINCE2 principle is being violated?

A project manager is assessing whether a new project to upgrade a data center complies with PRINCE2 principles. Which TWO of the following statements describe how the 'defined roles and responsibilities' principle is applied? (Choose two.)

During a project to implement a new enterprise resource planning system, the project manager realizes that the project's products are being defined in detail as they are being developed, rather than beforehand. The project manager wants to ensure that the project follows the PRINCE2 principle of 'focus on products'. What should the project manager do first?

A Project Manager is reviewing the PRINCE2 principles with the project team. The team is discussing how to ensure the project remains aligned with PRINCE2. Which TWO of the following statements correctly describe the PRINCE2 principles? (Choose two.)

A project manager is explaining the PRINCE2 principles to a new team member. The team member asks which principles are mandatory and must be applied without exception for the project to be considered PRINCE2-compliant. Which THREE of the following are PRINCE2 principles? (Choose three.)

A project manager is reviewing the PRINCE2 principles to ensure that the project is being managed correctly. Which TWO of the following are PRINCE2 principles? (Choose two.)

A project manager is reviewing the business case for a new software development project. The project is expected to generate significant revenue, but the initial investment is high. According to PRINCE2, which principle is MOST directly being applied when the project manager ensures that the business case remains viable throughout the project?

During a project, a key stakeholder raises a concern that the project scope has expanded significantly without formal approval. The project manager realizes that changes have been implemented informally. Which PRINCE2 principle has been violated?

A project team is working on a complex infrastructure project. The project manager wants to ensure that the project is tailored appropriately. According to PRINCE2, which principle addresses the need to adapt PRINCE2 to the project's specific context?

A project to build a new bridge is underway. The project board has decided to use a stage plan for the next stage rather than a detailed Gantt chart for the entire project. This approach aligns with which PRINCE2 principle?

A project manager notices that the project's product descriptions are being created after the products have already been developed. Which PRINCE2 principle is being ignored?

Which TWO of the following are PRINCE2 principles?

Which THREE of the following are PRINCE2 principles?

Refer to the exhibit. Which principle is missing from the configuration?

Exhibit

Refer to the exhibit.

PRINCE2 Configuration Block:
prince2 {
  project-name "Network Upgrade"
  version 2.0
  principles {
    continued-business-justification true
    learn-from-experience true
    defined-roles-and-responsibilities true
    manage-by-stages false
    manage-by-exception true
    focus-on-products true
    tailor-to-suit-project-environment true
  }
}

Free account

Track your progress over time

Create a free account to save your results and see which topics improve across sessions.

Focused Overview of PRINCE2 and Principles sessions

Start a Overview of PRINCE2 and Principles only practice session

Every question in these sessions is drawn from the Overview of PRINCE2 and Principles domain — nothing else.

Related practice questions

Related PRINCE2F topic practice pages

Move into related areas when this topic feels solid.

Frequently asked questions

What does the PRINCE2F exam test about Overview of PRINCE2 and Principles?
Be able to match a scenario to the correct PRINCE2 principle and spot which principle is being ignored. The single most important point: all seven principles are mandatory and cannot be tailored away, only how they are applied is tailored.
How should I use these practice questions?
Select your answer before revealing the explanation. Then read why each option is right or wrong — this active recall approach builds retention far faster than re-reading notes.
Can I practise just Overview of PRINCE2 and Principles questions in a focused session?
Yes — the session launcher on this page draws every question from the Overview of PRINCE2 and Principles domain. Use a 10-question session first to gauge your baseline, then move to 20 or 30 once the weak spots are clear.
Where can I practise other PRINCE2F topics?
Use the topic links above to move to related areas, or go back to the PRINCE2F question bank to see all topics.
Are these real exam questions or dumps?
These are original practice questions written to test the same concepts the PRINCE2F exam covers. They are not copied from any real exam or dump site.