Who chairs the Project Board meetings in PRINCE2?

⚠ Common exam trap

Candidates often confuse the Project Manager's role in facilitating meetings with the authority to chair the board, but PRINCE2 clearly separates management (Project Manager) from governance (Executive chairing the board).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Senior Responsible Owner (Executive)

The Executive (Senior Responsible Owner) chairs the Project Board meetings in PRINCE2 because they are ultimately accountable for the project's success and have the authority to make key decisions. This role ensures the project remains aligned with business objectives and provides strategic direction during board meetings.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Senior Supplier

    Why it's wrong here

    The Senior Supplier represents suppliers but does not chair.

  • Project Manager

    Why it's wrong here

    The Project Manager attends but does not chair.

  • Senior User

    Why it's wrong here

    The Senior User represents users but does not chair.

  • Senior Responsible Owner (Executive)

    Why this is correct

    The SRO chairs the Project Board.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Who chairs the Project Board meetings?

easy
  • A.Project Manager
  • B.Senior User
  • C.Senior Supplier
  • D.Executive (Senior Responsible Owner)

Why D: The Executive (Senior Responsible Owner) chairs the Project Board meetings.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.