Which role is ultimately accountable for the project's Business Case throughout the project?

⚠ Common exam trap

Candidates often confuse the Project Manager's responsibility for maintaining the Business Case document with the Executive's ultimate accountability for its content and the project's continued viability.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Senior Responsible Owner (Executive)

The Senior Responsible Owner (Executive) is ultimately accountable for the project's Business Case throughout its lifecycle. This role owns the Business Case and ensures the project remains viable, justified, and aligned with organizational objectives from initiation through closure.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User specifies needs and benefits and monitors that the solution delivers them, but accountability for the Business Case rests with the Executive. It tempts because users often articulate the benefits that justify the project, yet they only contribute to, rather than own, the business justification.

  • ✓

    Senior Responsible Owner (Executive)

    Why this is correct

    The Executive (Senior Responsible Owner) owns the Business Case and remains accountable for it throughout, ensuring the project stays aligned to benefits and justifies continued investment. This accountability cannot be delegated to the Project Manager, who only maintains and updates the Business Case on the Executive's behalf.

  • ✗

    Senior Supplier

    Why it's wrong here

    The Senior Supplier represents those delivering the products and is accountable for supplier resources and viability of the delivery, not the Business Case. It tempts because suppliers provide cost and effort data feeding the Business Case, but accountability for it sits with the Executive, who owns the business justification.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager prepares and maintains the Business Case on the Executive's behalf but is not ultimately accountable for it. It tempts because the role does the day-to-day updating and reviews, yet accountability for the business justification remains with the Executive, who owns the project's viability.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.