During the Initiation Stage, the project manager identifies that the selected team lacks experience with the chosen technology. What should the project manager do?
Trap 1: Replace the team members with experienced ones
This is a drastic action; the PM should first assess and plan.
Trap 2: Escalate to the Project Board for decision
Escalation may be needed later, but initially the PM should log the risk.
Trap 3: Update the Project Plan to include training
Training is a possible response, but first the risk must be documented.
- A
Replace the team members with experienced ones
Why it fails: This is a drastic action; the PM should first assess and plan.
- B
Escalate to the Project Board for decision
Why it fails: Escalation may be needed later, but initially the PM should log the risk.
- C
Update the Project Plan to include training
Why it fails: Training is a possible response, but first the risk must be documented.
- D
Update the Risk Register and plan a response
The skills gap is an uncertain event with potential impact on the project, so it belongs in the Risk Register with an owner, probability, impact and a planned response. This satisfies the Initiation Stage requirement to manage identified uncertainty formally.