A project manager is assigned to a new project. The project's business case has been approved, and the project board has authorized the initiation stage. According to PRINCE2, what is the first step the project manager should take?
Trap 1: Update the Risk Register
The Risk Register is created during the initiation stage but not necessarily as the first step.
Trap 2: Appoint the project board
The project board is appointed before the project is authorized.
Trap 3: Review the Business Case
The Business Case is already approved before initiation.
- A
Update the Risk Register
Why wrong: The Risk Register is created during the initiation stage but not necessarily as the first step.
- B
Appoint the project board
Why wrong: The project board is appointed before the project is authorized.
- C
Review the Business Case
Why wrong: The Business Case is already approved before initiation.
- D
Create the Project Plan
The Project Plan is the first plan to be created in the initiation stage.