A project is in the initiation stage. The project manager identifies that the project's objectives are not aligned with the corporate strategy. Which management product should the project manager review to address this issue?
Trap 1: Risk Register
The Risk Register lists risks, not objectives.
Trap 2: Business Case
The Business Case provides justification but does not detail alignment with strategy.
Trap 3: Project Plan
The Project Plan focuses on the project's approach and schedule.
- A
Project Brief
The Project Brief outlines the project's objectives and should align with corporate strategy.
- B
Risk Register
Why it fails: The Risk Register lists risks, not objectives.
- C
Business Case
Why it fails: The Business Case provides justification but does not detail alignment with strategy.
- D
Project Plan
Why it fails: The Project Plan focuses on the project's approach and schedule.