The Project Board has not met for several months. According to PRINCE2, when should the Project Board meet?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

At stage boundaries and when an Exception Report is raised

PRINCE2 recommends that Project Boards meet at the end of each management stage (Stage Boundary) and when an Exception Report is raised. They should not meet on a fixed monthly basis; meetings are exception-driven.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Weekly

    Why it's wrong here

    PRINCE2 does not mandate weekly Project Board meetings; the frequency is set by project needs and tolerance levels. Weekly would be correct for a high-risk, fast-moving project needing frequent direction, but as a fixed rule it misstates the standard, which ties meetings to decision points.

  • ✗

    Monthly

    Why it's wrong here

    PRINCE2 sets no fixed monthly cadence; the Project Board meets at decision points such as end stage assessments and exception reviews. Monthly would suit a stable project with predictable stage boundaries, but stating it as the rule misrepresents the standard, which is event-driven rather than calendar-driven.

  • ✓

    At stage boundaries and when an Exception Report is raised

    Why this is correct

    PRINCE2 mandates Project Board meetings at each stage boundary to authorise the next stage, and additionally whenever an Exception Report is escalated, since tolerances have been breached. This satisfies the stem's requirement by defining the two trigger points, rather than relying on a fixed calendar schedule.

  • ✗

    Only at the end of the project

    Why it's wrong here

    PRINCE2 requires the Project Board to meet at defined decision points, including end stage assessments and exception situations, not solely at project closure. Meeting only at the end would leave stage boundaries unapproved and exceptions unmanaged, so this timing fails the governance the Board must provide.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.