Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

The Project Manager has produced an End Stage Report for the current stage. According to PRINCE2, what is the next step?

⚠ Common exam trap

A common misconception in the PRINCE2 exam is that the Project Manager can unilaterally proceed to the next stage after producing the End Stage Report, when in fact PRINCE2 mandates that the Project Board must formally authorize the next stage.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit the report to the Project Board for a decision on whether to proceed

In PRINCE2, the End Stage Report is produced by the Project Manager to provide the Project Board with a summary of the stage's performance. The next step is to submit this report to the Project Board, which then decides whether to authorize the next stage, amend the project, or stop the project. Option D correctly reflects this governance checkpoint, as the Project Board holds the authority to approve continued investment.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.