PRINCE2F People: organizations, teams, and leadership Practice Question
Who is responsible for ensuring that Project Assurance is performed?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Board
The Project Board is accountable for the project and must ensure that independent assurance is in place. The Executive (SRO) often appoints assurance roles, but ultimate responsibility lies with the Project Board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Project Board
Why this is correct
The Project Board is responsible for ensuring that Project Assurance is performed independently.
- ✗
Project Manager
Why it's wrong here
The Project Manager cannot be responsible for assurance as it must be independent of management.
- ✗
Senior Supplier
Why it's wrong here
The Senior Supplier may provide assurance from the supplier perspective, but the Board as a whole is responsible.
- ✗
Team Manager
Why it's wrong here
The Team Manager is focused on delivering Work Packages, not assurance.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.