Who is responsible for authorizing the initiation of a project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The Project Board

The Project Board, as part of the Directing a Project process, authorizes the initiation stage. The Executive chairs the Board but authorization is a Board decision.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The Senior User

    Why it's wrong here

    The Senior User is part of the Board but authorization is by the Board collectively.

  • The Project Manager

    Why it's wrong here

    The PM manages the project but does not authorize initiation.

  • The Project Board

    Why this is correct

    The Project Board authorizes initiation in the Directing a Project process.

  • The Executive

    Why it's wrong here

    While the Executive is a key Board member, authorization is a collective Board decision.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.