Which TWO of the following are true about the Managing a Stage Boundary process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
It produces the End Stage Report
SB is performed near the end of each stage (except the final) to produce an End Stage Report, plan the next stage, and update the Project Plan. It also captures lessons and can produce an Exception Plan if needed.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
It produces the End Stage Report
Why this is correct
The End Stage Report is a key output of SB.
- ✗
It is performed at the end of every stage, including the final stage
Why it's wrong here
SB is not performed for the final stage; Closing a Project is used.
- ✗
It authorises the initiation of the next stage
Why it's wrong here
Authorisation is done by the Board in DP, not in SB.
- ✓
It updates the Project Plan with progress and new stage plans
Why this is correct
The Project Plan is updated in SB.
- ✗
It includes the creation of the Business Case
Why it's wrong here
The Business Case is created in SU and refined in IP and later stages.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.