PRINCE2F PRINCE2 Processes Practice Question
Which TWO of the following are produced during the Initiating a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Risk Management Approach
IP produces the PID, which includes the Risk Management Approach and Communication Management Approach. The Project Brief is from SU, and the End Stage Report is from SB.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Brief
Why it's wrong here
Produced in SU.
- ✗
End Stage Report
Why it's wrong here
Produced in SB.
- ✓
Risk Management Approach
Why this is correct
Created in IP as part of PID.
- ✓
Communication Management Approach
Why this is correct
Created in IP as part of PID.
- ✗
Exception Report
Why it's wrong here
Produced in CS when tolerances are exceeded.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.