PRINCE2 ProcessesmediumMultiple SelectObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Which TWO of the following are produced during the Initiating a Project process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Risk Management Approach

IP produces the PID, which includes the Risk Management Approach and Communication Management Approach. The Project Brief is from SU, and the End Stage Report is from SB.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Brief

    Why it's wrong here

    Produced in SU.

  • End Stage Report

    Why it's wrong here

    Produced in SB.

  • Risk Management Approach

    Why this is correct

    Created in IP as part of PID.

  • Communication Management Approach

    Why this is correct

    Created in IP as part of PID.

  • Exception Report

    Why it's wrong here

    Produced in CS when tolerances are exceeded.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.