Courseiva
PRINCE2 ProcesseseasyMultiple SelectObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Which TWO of the following are outputs of the Starting Up a Project process?

⚠ Common exam trap

In PRINCE2 exams, candidates often confuse the outputs of Starting Up a Project (SU) with those of Initiating a Project (IP). The Project Brief is an output of SU, while the Project Initiation Documentation is an output of IP. The Benefits Management Approach is developed later in the process, not during SU.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Initiation Stage Plan

The Starting Up a Project process is the first process in PRINCE2, occurring before the project is formally initiated. Its purpose is to ensure that the project has a viable and worthwhile business justification, and that the necessary authorities exist to proceed. The Initiation Stage Plan is a key output because it plans the work required for the Initiation Stage, which is the next step after Starting Up a Project. The Project Brief is also a core output, as it provides a high-level overview of the project's scope, objectives, and approach, which is used to justify proceeding to initiation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Initiation Stage Plan

    Why this is correct

    The Stage Plan for initiation is created in SU.

  • Benefits Management Approach

    Why it's wrong here

    Benefits Management Approach is created in IP.

  • Project Brief

    Why this is correct

    The Project Brief is a key output of SU.

  • End Project Report

    Why it's wrong here

    End Project Report is from Closing a Project.

  • Project Initiation Documentation

    Why it's wrong here

    PID is an output of Initiating a Project.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.