PRINCE2F Practice Question: Overview of PRINCE2 and the project environment
Which THREE of the following are responsibilities of the Project Board?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Ensuring continued business justification
The Project Board is accountable for the Business Case, approves plans, and authorizes stage transitions.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Providing day-to-day management of the project
Why it's wrong here
That is the Project Manager's role.
- ✓
Ensuring continued business justification
Why this is correct
The Board oversees the Business Case.
- ✓
Authorizing stage transitions
Why this is correct
The Board approves movement between stages.
- ✓
Approving the Project Plan
Why this is correct
The Board approves major plans.
- ✗
Assigning work packages to teams
Why it's wrong here
The Project Manager assigns work packages.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.