Which THREE of the following are responsibilities of the Project Manager during the Controlling a Stage process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Review the stage status and take corrective action

The Project Manager in Controlling a Stage authorises Work Packages, monitors progress, and reports to the Project Board via Highlight Reports. The Project Board authorises stage plans, and the Team Manager produces Checkpoint Reports.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Produce Checkpoint Reports

    Why it's wrong here

    Producing Checkpoint Reports is a responsibility of the Team Manager, not the Project Manager. During the Controlling a Stage process, the Project Manager's role is to receive and review these reports from the Team Manager to monitor progress and take corrective action. This option is tempting because Checkpoint Reports are a critical input for the Project Manager to exercise control and make informed decisions. However, the Project Manager does not originate them; they would be a correct choice if the question concerned the Team Manager's responsibilities or the information flowing *to* the Project Manager.

  • Authorise the next Stage Plan

    Why it's wrong here

    Authorising stage plans is the Project Board's responsibility in Directing a Project.

  • Review the stage status and take corrective action

    Why this is correct

    Correct. The PM monitors and takes action within tolerances.

  • Produce Highlight Reports

    Why this is correct

    Correct. The PM produces Highlight Reports for the Board.

  • Authorise Work Packages

    Why this is correct

    Correct. The PM authorises work packages.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.