Courseiva
PRINCE2 PracticeshardMultiple SelectObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

Which THREE of the following are PRINCE2 management products that contain baselines?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Stage Plan

The Project Plan, Stage Plans, and Product Descriptions are baselined. Highlight Reports are reports, not baselines. The Issue Register records issues but is not a baseline.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Stage Plan

    Why this is correct

    Stage Plans are baselined at the start of each stage.

  • Issue Register

    Why it's wrong here

    The Issue Register is a log, not a baseline.

  • Highlight Report

    Why it's wrong here

    Highlight Reports are periodic reports, not baselines.

  • Project Plan

    Why this is correct

    The Project Plan is baselined at project initiation.

  • Product Description

    Why this is correct

    Product Descriptions are baselined when the product is approved.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.