PRINCE2F PRINCE2 Practices Practice Question
Which THREE of the following are PRINCE2 management products that contain baselines?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Stage Plan
The Project Plan, Stage Plans, and Product Descriptions are baselined. Highlight Reports are reports, not baselines. The Issue Register records issues but is not a baseline.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Stage Plan
Why this is correct
Stage Plans are baselined at the start of each stage.
- ✗
Issue Register
Why it's wrong here
The Issue Register is a log, not a baseline.
- ✗
Highlight Report
Why it's wrong here
Highlight Reports are periodic reports, not baselines.
- ✓
Project Plan
Why this is correct
The Project Plan is baselined at project initiation.
- ✓
Product Description
Why this is correct
Product Descriptions are baselined when the product is approved.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.