PRINCE2F PRINCE2 Processes Practice Question
Which THREE of the following are outputs of the Initiating a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Quality Management Approach
The Initiating a Project process produces the Project Initiation Documentation (PID), which includes the Project Plan, Business Case, and various management approaches. The Project Brief is an output of SU, and the End Stage Report is from SB.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Brief
Why it's wrong here
Project Brief is an output of Starting Up a Project, not IP.
- ✓
Quality Management Approach
Why this is correct
The Quality Management Approach is one of the management approaches produced in IP.
- ✗
End Stage Report
Why it's wrong here
End Stage Report is an output of Managing a Stage Boundary.
- ✓
Business Case
Why this is correct
The Business Case is developed and refined in IP as part of the PID.
- ✓
Project Plan
Why this is correct
The Project Plan is a key component of the PID produced in IP.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.