PRINCE2F PRINCE2 Practices Practice Question
Which THREE of the following are components of the PRINCE2 quality management approach?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Quality control methods (e.g., quality review technique)
The Quality Management Approach includes standards, quality control methods, and quality assurance. The Quality Register is a separate document, not part of the approach. The Project Plan is also separate.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Quality control methods (e.g., quality review technique)
Why this is correct
Methods are defined in the approach.
- ✓
Roles and responsibilities for quality
Why this is correct
Included in the approach.
- ✗
Project Plan
Why it's wrong here
The Project Plan is a separate document.
- ✓
Quality standards and procedures to be applied
Why this is correct
Part of the approach.
- ✗
Quality Register
Why it's wrong here
The Quality Register is a log of quality activities, not part of the approach definition.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
2 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which THREE of the following are components of the PRINCE2 quality management approach?
hard- A.Product descriptions
- B.Quality register
- ✓ C.Quality assurance approach
- ✓ D.Roles and responsibilities for quality
- ✓ E.Quality control methods
Why C: The quality management approach includes the quality control methods, quality assurance approach, and the roles and responsibilities for quality.
Variation 2. Which TWO of the following are components of the PRINCE2 quality management approach?
medium- A.The quality register
- ✓ B.The quality responsibilities of the project management team
- C.The project assurance responsibilities
- D.The quality review technique
- ✓ E.The quality methods and tools to be used
Why B: The quality management approach documents the specific quality methods and tools to be used (option E) and the quality responsibilities of the project management team (option B). The quality register (option A) is a log used to record quality activities, not part of the approach itself. Project assurance responsibilities (option C) are defined in the project management team structure, not in the quality management approach. The quality review technique (option D) is a specific method that may be included as part of the quality methods, but it is not a component of the approach; the approach describes the overall methods and tools.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.