PRINCE2F PRINCE2 Processes Practice Question
Which THREE of the following are activities performed in the Controlling a Stage process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Review progress against the Stage Plan
CS includes activities like authorizing Work Packages, managing issues, and reviewing progress. Closing the project is CP; creating the Project Plan is IP.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Create the Project Plan
Why it's wrong here
Done in IP.
- ✓
Review progress against the Stage Plan
Why this is correct
CS includes reviewing progress.
- ✓
Authorize Work Packages
Why this is correct
CS includes authorizing Work Packages.
- ✗
Close the project
Why it's wrong here
Done in CP.
- ✓
Escalate issues and risks to the Project Board
Why this is correct
CS includes escalation when tolerances are exceeded.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.