PRINCE2 ProcesseshardMultiple SelectObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Which THREE of the following are activities performed during the Controlling a Stage process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Review the stage status

CS includes authorizing Work Packages, reviewing progress, and escalating issues. Planning the next stage is done in Managing a Stage Boundary. Authorizing the project is done in Directing a Project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Authorize the project

    Why it's wrong here

    Authorizing the project is done in Directing a Project.

  • Plan the next stage

    Why it's wrong here

    Planning the next stage is done in Managing a Stage Boundary.

  • Review the stage status

    Why this is correct

    The PM reviews progress against the Stage Plan.

  • Authorize a Work Package

    Why this is correct

    This is a key activity in CS.

  • Escalate issues to the Project Board

    Why this is correct

    If tolerances are exceeded, the PM raises an Exception Report.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.