PRINCE2F PRINCE2 Processes Practice Question
Which THREE of the following are activities performed during the Controlling a Stage process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Review the stage status
CS includes authorizing Work Packages, reviewing progress, and escalating issues. Planning the next stage is done in Managing a Stage Boundary. Authorizing the project is done in Directing a Project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Authorize the project
Why it's wrong here
Authorizing the project is done in Directing a Project.
- ✗
Plan the next stage
Why it's wrong here
Planning the next stage is done in Managing a Stage Boundary.
- ✓
Review the stage status
Why this is correct
The PM reviews progress against the Stage Plan.
- ✓
Authorize a Work Package
Why this is correct
This is a key activity in CS.
- ✓
Escalate issues to the Project Board
Why this is correct
If tolerances are exceeded, the PM raises an Exception Report.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.