PRINCE2 ProcessesmediumMultiple SelectObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Which THREE of the following are activities performed during the Controlling a Stage process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Authorise Work Packages

CS includes authorising Work Packages, reviewing progress, reporting highlights, and managing issues and risks.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Authorise Work Packages

    Why this is correct

    Yes, the PM authorises Work Packages in CS.

  • Produce the End Stage Report

    Why it's wrong here

    End Stage Report is produced in SB.

  • Produce the Project Plan

    Why it's wrong here

    Project Plan is produced in IP and updated in SB.

  • Report on progress to the Project Board via Highlight Reports

    Why this is correct

    Yes, Highlight Reports are sent from CS.

  • Take corrective action to keep the stage within tolerance

    Why this is correct

    Yes, the PM takes corrective action within stage tolerance in CS.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.