Which THREE of the following are activities performed during the Controlling a Stage process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Authorise Work Packages
CS includes authorising Work Packages, reviewing progress, reporting highlights, and managing issues and risks.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Authorise Work Packages
Why this is correct
Yes, the PM authorises Work Packages in CS.
- ✗
Produce the End Stage Report
Why it's wrong here
End Stage Report is produced in SB.
- ✗
Produce the Project Plan
Why it's wrong here
Project Plan is produced in IP and updated in SB.
- ✓
Report on progress to the Project Board via Highlight Reports
Why this is correct
Yes, Highlight Reports are sent from CS.
- ✓
Take corrective action to keep the stage within tolerance
Why this is correct
Yes, the PM takes corrective action within stage tolerance in CS.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.