Which statement best describes the difference between Starting Up a Project (SU) and Initiating a Project (IP)?

⚠ Common exam trap

PRINCE2 often tests the confusion between the outputs of SU and IP, specifically that SU appoints roles and produces the Project Brief, while IP produces the PID and detailed plans, not the other way around.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

SU appoints the Project Board and Project Manager, while IP develops the PID

Starting Up a Project (SU) is the process that ensures the prerequisites for initiating a project are in place, including appointing the Project Board and Project Manager. Initiating a Project (IP) then develops the Project Initiation Documentation (PID), which formalizes the project's scope, plans, and controls. Thus, D correctly distinguishes the key outputs of these two processes.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • SU produces the Stage Plan for the initiation stage, while IP produces the Project Plan

    Why it's wrong here

    Both statements are true but not the best distinguishing description.

  • SU is performed by the Project Board, while IP is performed by the Project Manager

    Why it's wrong here

    SU is led by the Executive/PM; IP is led by the PM.

  • SU selects the project mandate, while IP develops the project brief

    Why it's wrong here

    The project mandate is an input; SU produces the Project Brief.

  • SU appoints the Project Board and Project Manager, while IP develops the PID

    Why this is correct

    SU appoints key roles and creates the Project Brief; IP creates the PID and detailed plans.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. What is the main difference between the Starting Up a Project process and the Initiating a Project process?

medium
  • A.SU is done by the Project Manager; IP is done by the Project Board
  • B.SU includes risk management; IP does not
  • C.SU creates the Project Brief; IP creates the Project Initiation Documentation
  • D.SU is optional; IP is mandatory

Why C: SU is a pre-project process to determine if the project is viable and worth initiating, while IP formally establishes the project foundation with detailed plans.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.