PRINCE2F PRINCE2 Processes Practice Question
Which process is responsible for authorizing the work to be done in a stage?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Directing a Project
The Directing a Project process is where the Project Board authorizes the work for each stage, including the initiation stage and subsequent stages.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Directing a Project
Why this is correct
Correct. The Project Board authorizes stage plans via DP.
- ✗
Initiating a Project
Why it's wrong here
IP establishes the project but does not authorize subsequent stages; that is done by DP.
- ✗
Starting Up a Project
Why it's wrong here
SU is pre-project and does not authorize stage work.
- ✗
Controlling a Stage
Why it's wrong here
CS is the PM's process for managing day-to-day work, not authorizing stages.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.