PRINCE2F PRINCE2 Processes Practice Question

Which process is responsible for authorizing the initiation of a project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Directing a Project

The Project Board, through the Directing a Project process, authorizes the initiation of a project after reviewing the outputs from Starting Up a Project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Directing a Project

    Why this is correct

    DP includes the decision to authorize initiation.

  • Starting Up a Project

    Why it's wrong here

    SU prepares the project brief but does not authorize initiation.

  • Controlling a Stage

    Why it's wrong here

    CS is concerned with managing ongoing stages.

  • Initiating a Project

    Why it's wrong here

    IP is performed after authorization to initiate.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.