Question 1,521 of 1,599
PRINCE2F PRINCE2 Processes Practice Question
Which process is responsible for authorizing the initiation of a project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Directing a Project
Directing a Project (DP) is the process where the Project Board makes key decisions, including authorizing initiation. Starting Up a Project (SU) prepares the conditions but does not authorize initiation.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Directing a Project
Why this is correct
The Project Board authorizes initiation under DP.
- ✗
Initiating a Project
Why it's wrong here
IP is the process of establishing the project; authorization comes from DP.
- ✗
Starting Up a Project
Why it's wrong here
SU prepares the Project Brief and initiation Stage Plan but does not authorize initiation.
- ✗
Controlling a Stage
Why it's wrong here
CS manages day-to-day work within a stage, not authorization of initiation.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 21, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.