Which of the following statements about Starting Up a Project (SU) and Initiating a Project (IP) is true?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
SU is a pre-project process that decides if the project is viable
SU is a pre-project process that ensures the project is viable before committing to full initiation. IP formally establishes the project and produces the PID.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
IP is the first process after the Project Board authorizes the project
Why it's wrong here
The first process after authorization is Controlling a Stage, not IP. IP occurs after SU.
- ✓
SU is a pre-project process that decides if the project is viable
Why this is correct
SU checks the basic conditions and decides whether to proceed to initiation.
- ✗
SU produces the Project Initiation Documentation (PID)
Why it's wrong here
The PID is produced during IP, not SU.
- ✗
IP is optional if the Project Brief is approved in SU
Why it's wrong here
IP is mandatory to establish the project on a solid foundation.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.