Correct answer & explanation
✓
Project Plan
The Business Case components include reasons, options, expected benefits, dis-benefits, timescale, costs, investment appraisal, and major risks. The Project Plan is a separate management product.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Expected benefits
Why it's wrong here
Expected benefits are a component of the Business Case.
- ✓
Project Plan
Why this is correct
The Project Plan is not a component of the Business Case.
- ✗
Investment appraisal
Why it's wrong here
Investment appraisal is part of the Business Case.
- ✗
Major risks
Why it's wrong here
Major risks are included in the Business Case.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.