Which of the following is NOT a component of the Business Case?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Plan

The Business Case components include reasons, options, expected benefits, dis-benefits, timescale, costs, investment appraisal, and major risks. The Project Plan is a separate management product.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Expected benefits

    Why it's wrong here

    Expected benefits are a component of the Business Case.

  • Project Plan

    Why this is correct

    The Project Plan is not a component of the Business Case.

  • Investment appraisal

    Why it's wrong here

    Investment appraisal is part of the Business Case.

  • Major risks

    Why it's wrong here

    Major risks are included in the Business Case.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.