PRINCE2F PRINCE2 Practices Practice Question
Which document is the key output of the Initiating a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Initiation Documentation
The Project Initiation Documentation (PID) is the key output that defines the project and provides a baseline for decision-making.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Project Initiation Documentation
Why this is correct
The PID is the key output of Initiating a Project.
- ✗
Project Plan
Why it's wrong here
The Project Plan is part of the PID but not the key output alone.
- ✗
Project Brief
Why it's wrong here
The Project Brief is created in Starting Up a Project.
- ✗
Business Case
Why it's wrong here
The Business Case is refined during initiation but is not the sole key output.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.