Which document is the key output of the Initiating a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Initiation Documentation (PID)
The Project Initiation Documentation (PID) is the key output of the Initiating a Project process, providing the foundation for the project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Brief
Why it's wrong here
The Project Brief is created in Starting Up a Project, not Initiating a Project.
- ✗
Project Plan
Why it's wrong here
The Project Plan is part of the PID but the PID is the overall output.
- ✗
Business Case
Why it's wrong here
The Business Case is developed earlier, but refined in Initiating a Project and included in the PID.
- ✓
Project Initiation Documentation (PID)
Why this is correct
Correct. The PID is the key output of Initiating a Project.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.