Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

What is the purpose of the Starting Up a Project process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

To ensure there is a viable Business Case and that the project team is appointed

SU ensures that the project has a viable Business Case and that the necessary people are appointed before committing to the full initiation effort.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • To approve the project mandate

    Why it's wrong here

    The project mandate is an input, not an output of SU.

  • To manage the delivery of products

    Why it's wrong here

    Product delivery is managed in Managing Product Delivery.

  • To ensure there is a viable Business Case and that the project team is appointed

    Why this is correct

    SU establishes the basic conditions for the project to proceed.

  • To develop the Project Initiation Documentation

    Why it's wrong here

    The PID is developed in Initiating a Project, not SU.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.