The project manager notices that a team member has not completed a critical product according to the quality criteria. What should the project manager do first?

⚠ Common exam trap

Watch out — candidates often confuse the project manager's role with the team manager's role, incorrectly assuming the project manager must immediately escalate to the Project Board (Option C) rather than first instructing the team manager to correct the product within the delegated tolerance.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Instruct the team manager to correct the product within the work package tolerance

The correct first action is to instruct the team manager to correct the product within the work package tolerance. In PRINCE2, the project manager manages by exception; if a team member fails to meet quality criteria, the project manager should first escalate to the team manager (who manages the work package) to resolve the issue within the agreed tolerances. This aligns with the 'Managing Product Delivery' process, where the team manager is responsible for delivering products to specification.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the Project Plan to reflect the delay

    Why it's wrong here

    Updating the Project Plan is part of SB, not a first response.

  • Close the project as the quality criteria are not met

    Why it's wrong here

    Closing the project is too drastic for a single quality issue.

  • Raise an Exception Report to the Project Board

    Why it's wrong here

    Only if the tolerance is forecast to be exceeded, not for a single quality issue that might be corrected.

  • Instruct the team manager to correct the product within the work package tolerance

    Why this is correct

    Correct. The PM should manage the issue within the stage; the team manager can take corrective action.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.