PRINCE2F PRINCE2 Processes Practice Question
The project manager is preparing the next Stage Plan during the Managing a Stage Boundary process. Which document should be used as the basis for updating the Business Case?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The End Stage Report
The End Stage Report provides the current stage's performance, which feeds into the Business Case update. The Benefits Management Approach and other documents are also considered, but the End Stage Report is key for performance data.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The Project Brief
Why it's wrong here
The Project Brief is from SU and not updated during SB.
- ✗
The project's risk register
Why it's wrong here
The risk register is an input but not the primary basis for BC update.
- ✓
The End Stage Report
Why this is correct
Correct. The End Stage Report provides actual results vs planned, informing the BC update.
- ✗
The Quality Management Approach
Why it's wrong here
Quality approach is not the basis for BC update.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.