Refer to the exhibit.

Project: Alpha
Stage: Stage 2
Work Package: WP-003
Status: Completed
Actual Cost: $45,000
Planned Cost: $40,000
% Complete: 100%

Tolerance: Cost: +/- 10%

Refer to the exhibit. The project manager is reviewing a completed work package in Stage 2. The actual cost exceeds the planned cost by $5,000. What should the project manager do?

⚠ Common exam trap

It's easy for candidates to assume a completed work package with a cost overrun can simply be accepted or recorded, but PRINCE2 requires escalation whenever tolerances are exceeded, regardless of completion status.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Escalate the issue to the project board as an exception.

The work package is complete but the actual cost exceeds the planned cost by $5,000, which exceeds the tolerance set for the work package. In PRINCE2, any deviation beyond the agreed tolerance must be escalated to the Project Board as an exception, as the Project Manager cannot approve such variances themselves.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the project plan to reflect the actual cost.

    Why it's wrong here

    Updating the plan comes after the issue is resolved; first, escalate the exception.

  • Record the actual cost and continue with the project.

    Why it's wrong here

    The actual cost exceeds tolerance, so an exception report is needed before continuing.

  • Escalate the issue to the project board as an exception.

    Why this is correct

    Since the cost variance exceeds the work package tolerance, the project manager must escalate via an exception report.

  • Accept the variance as the work package is complete.

    Why it's wrong here

    The variance exceeds the 10% tolerance, so it cannot be accepted without escalation.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.