During the Managing Product Delivery process, what is used to assign work to the Team Manager?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Work Package

The Project Manager authorises a Work Package to assign work to the Team Manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Stage Plan

    Why it's wrong here

    Stage Plan is the plan for the stage; not the assignment document.

  • Project Plan

    Why it's wrong here

    Project Plan is a high-level plan, not an assignment document.

  • Work Package

    Why this is correct

    Work Package is the formal authorisation to deliver products.

  • Product Description

    Why it's wrong here

    Product Description defines the product but is part of the Work Package.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.