During the Closing a Project process, which document is used to confirm that the project's products have been accepted?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

End Project Report

The End Project Report confirms acceptance of products and provides a summary of project performance.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Product Description

    Why it's wrong here

    The Project Product Description defines the product but does not confirm acceptance.

  • End Project Report

    Why this is correct

    The End Project Report includes confirmation of product acceptance.

  • Benefits Management Approach

    Why it's wrong here

    This approach plans benefits reviews but does not confirm product acceptance.

  • Lessons Report

    Why it's wrong here

    The Lessons Report captures lessons learned, not product acceptance.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.