During the Closing a Project process, which document is used to confirm that the project's products have been accepted?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
End Project Report
The End Project Report confirms acceptance of products and provides a summary of project performance.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Product Description
Why it's wrong here
The Project Product Description defines the product but does not confirm acceptance.
- ✓
End Project Report
Why this is correct
The End Project Report includes confirmation of product acceptance.
- ✗
Benefits Management Approach
Why it's wrong here
This approach plans benefits reviews but does not confirm product acceptance.
- ✗
Lessons Report
Why it's wrong here
The Lessons Report captures lessons learned, not product acceptance.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.