Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

A Work Package is being executed by the Team Manager. During this, the Team Manager identifies a new risk that could delay delivery. What should the Team Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Update the Risk Register and inform the Project Manager

The Team Manager manages the Work Package and reports issues/risks to the Project Manager via Checkpoint Reports and the Issue Register.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the Risk Register and inform the Project Manager

    Why this is correct

    The Team Manager should log the risk and escalate to the PM.

  • Update the Project Plan

    Why it's wrong here

    The PM updates the Project Plan, not the Team Manager.

  • Stop work and wait for instructions

    Why it's wrong here

    The Team Manager should continue unless instructed otherwise.

  • Inform the Project Board directly

    Why it's wrong here

    The Team Manager reports to the PM, not the board.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.